PGE, Aceh?s SOE team up to develop geothermal
Tuesday, May 10 2016 - 03:27 PM WIB
The agreement was signed by PGE?s President Director Irfan Zainuddin and PDPA?s President Director Muhsin in the presence of Pertamina?s President Director Dwi Soetjipto and Aceh?s Governor Zaini Abdullah, Pertamina?s spokesperson Wianda Pusponegoro said in a statement.
The working area has potentials to generate up to 165 MW of power. The government has assigned PGE to develop the working area.
Both firms will set up a joint venture in which PGE will have a 75 percent interest and PDPA the remainder. In the first phase, the joint venture will carry out survey and exploration to develop the first power generation unit with a capacity of 55 MW and investment commitment of US$40 million.
The Seulawah Agam working area is located in Aceh Besar regency, spanning across several sub-districts, namely Seulimeum, Krueng Raya and Indrapuri. The project?s location is 50km southeast of Banda Aceh, the province?s capital.
Editing by Johannes Simbolon