PGE targets installed capacity of 847 MW by 2018

Wednesday, March 5 2014 - 09:33 AM WIB

By Febry Silaban

PT Pertamina Geothermal Energy (PGE), a wholly owned subsidiary of state-owned oil and gas firm PT Pertamina (Persero), is aiming to increase its power generation capacity to 847 MW by 2018.

"Currently (2014), our installed capacity is 402 MW. God willing, by 2018 the capacity will reach 847 MW, which means more than double within 4 years," said PGE's President Director Rony Gunawan, in Jakarta, on Tuesday.

He said various constraints are confronting the company such as difficulties to get permits from the Ministry of Forestry, because most of the PGE?s working areas overlap conservation and protection forest, so the licensing process takes a long time.

"We continue facing challenges in our efforts to increase the installed capacity," he said.

Rony also added PGE is aiming to increase its power generation capacity to 2.3 gigawatts (GW) by 2025, five times of the current capacity.

Installed capacity plan for 2014-2018

  2014 2015 2016 2017 2018
Tenement 402 MW 437 MW 597 MW 737 MW 847 MW
Kemojang & Ciharus 200 MW 235 MW 235 MW 235 MW 235 MW
Lahendong & Tompaso 80 MW 80 MW 100 MW 130 MW 130 MW
Sibayak & Sinabung 12 MW 12 MW 12 MW 12 MW 12 MW
Ulubelu & Way Panas 110 MW 110 MW 165 MW 220 MW 220 MW
Lumutbalai & Margabayur - - 55 MW 55 MW 110 MW
Hululais & Tambang Sawah - - - 55 MW 110 MW
Kotamobagu - - - - -
Sungai Penuh - - - - -
Karaha - - 30 MW 30 MW 30 MW