PLN a step closer to developing Tulehu power plant in Maluku
Wednesday, November 20 2013 - 02:22 AM WIB
The signing was inked by PLN President Director Nur Pamudji, West JEC President Director Hiroshi Nagano and Connusa President Director Kohar Sutomo.
West JEC and Connusa will team up to carry our engineering service works for the power plant which is located in Salahutu, Central Maluku Regency, Maluku.
The works include reviews and analysis on study results, engineering design, pre-qualification and tender documents, tender, contract evaluation and negotiation, construction supervision and post construction services.
The contract will take effect immediately after the signing of a funding agreement for the project with JICA, which is expected soon.
The Tulehu project is a part of PLN's second 10,000 MW electricity generation crash program.
Editing by Dadan Wijaksana