Adaro Energy update: Indonesia Bulk Terminal (IBT)

Friday, July 29 2011 - 02:45 AM WIB

The following is an edited excerpt from IDX-listed energy firm PT.Adaro Energy 's second quarter report released on Thursday. (ed)

PT Indonesia Bulk Terminal (IBT)?Coal Terminal Services (100%)

In 2Q11, total coal shipped and the number of vessels loaded decreased as AI moved more of its transhipment activities to the more convenient and closer Taboneo anchorage. Coal shipped decreased 4% to 1.23 million tonnes. However, tonnage increased 50% compared to 1Q11 due to new customers. (end of edited excerpt)

Year on Year Units 2Q11 2Q10 % Change
Total Coal Shipped Mt 1.23 1.28 -4%
Adaro/Coaltrade Mt 0.58 0.81 -29%
Third party Mt 0.65 0.47 39%
No of vessels loaded   18 20 -10%
Quarter on Quarter Units 2Q11 1Q11 % Change
Total Coal Shipped Mt 1.23 0.82 50%
Adaro/Coaltrade Mt 0.58 0.43 34%
Third party Mt 0.65 0.39 67%
No of vessels loaded   18 12 50%
1H11 vs. 1H10 Units 1H11 1H10 % Change
Total Coal Shipped Mt 2.05 3.03 -32%
Adaro/Coaltrade Mt 1.01 1.93 -48%
Third Party Mt 1.04 1.10 -5%
No of vessels loaded   30 48 -38%