Adaro Energy update: Indonesia Bulk Terminal (IBT)

Friday, April 27 2012 - 01:43 AM WIB

The following is an edited excerpt from IDX-listed energy firm PT.Adaro Energy 's quarterly report released on Thursday. (ed)

Coal Terminal: PT Indonesia Bulk Terminal (IBT)(100%)

In 1Q12, total coal loaded increased 25% to 1.03 million tonnes mainly due to the increase in third parties? performance. The number of vessels loaded also increased 33% to 16 vessels. (end of edited excerpt)

Year on Year Units 1Q12 1Q11 % Change
Total Coal Loade Mt 1.03 0.82 25%
Adaro/Coaltrade Mt 0.36 0.50 -28%
Third Party Mt 0.66 0.32 106%
No of Vessels Loaded 16 12 33%
Quarter on Quarter Units 1Q12 1Q11 % Change
Total Coal Loade Mt 1.03 0.93 10%
Adaro/Coaltrade Mt 0.36 0.44 -17%
Third Party Mt 0.66 0.49 35%
No of Vessels Loaded 16 14 14%