The following is an edited excerpt from IDX-listed energy firm PT.Adaro Energy 's third quarter report released on Monday. (ed)

Orchard Maritime Logistics Ltd (OML), PT Maritim Barito Perkasa (MBP) and PT Harapan Bahtera Internusa (HBI) - Barging and Ship Loading Contractor (95% - 100% - 100%)

In 3Q11, total coal barged increased 65% to 4.54 million tonnes due to a shorter cycle time at Taboneo anchorage as well as a new third party contract awarded at the beginning of this year. Total coal loaded also increased 65% to 4.22 million tonnes, as two of our floating cranes that were under maintenance since 1Q11 were back in full operation. Our barging and ship loading contractor is on track to achieve its target of 14.8 million tonnes of barged coal and 13.5 million tonnes of coal loaded. (end of edited excerpt)

Year on Year Units 3Q11 3Q10 % Change
Total Coal Barged Mt 4.54 2.75 65%
Adaro Mt 4.25 2.61 63%
Others Mt 0.29 0.14 106%
Total Coal Loaded Mt 4.22 2.55 65%
Adaro Mt 4.22 2.41 75%
Others Mt - 0.14 -100%
Quarter on Quarter Units 3Q11 3Q10 % Change
Total Coal Barged Mt 4.54 3.71 22%
Adaro Mt 4.25 3.20 33%
Others Mt 0.29 0.51 -44%
Total Coal Loaded Mt 4.22 2.56 65%
Adaro Mt 4.22 2.56 65%
Others Mt - 0.01 -100%
9H11 vs. 9H10 Units 9M11 9M10 % Change
Total Coal Barged Mt 11.60 8.58 35%
Adaro Mt 10.38 7.92 31%
Others Mt 1.22 0.66 85%
Total Coal Loaded Mt 9.75 9.17 6%
Adaro Mt 9.68 9.03 7%
Others Mt 0.07 0.14 -48%