Adaro Energy update: Project Development
Tuesday, February 4 2014 - 11:53 PM WIB
The following is an edited excerpt from IDX-listed energy firm PT.Adaro Energy's quarterly report released on Tuesday. (ed)
Out of Pit Overburden Crusher and Conveyor
The physical construction of OPCC is complete and testing stage was still underway.
Capacity Expansion at the Kelanis River Terminal
During 4Q13, we continued a detailed planning for the second upgrade of the Kelanis River Terminal to bring total capacity to 70 Mt per year. We completed the first stage of expansion to bring the capacity to 66 Mt per year. (end of edited excerpt)