Adaro Energy update: Project Development

Wednesday, April 30 2014 - 12:13 AM WIB

The following is an edited excerpt from IDX-listed energy firm PT.Adaro Energy's quarterly report released on Tuesday. (ed)

Out of Pit Overburden Crusher and Conveyor (OPCC)
We completed the physical construction of the OPCC in 2013, and are now doing reliability testing. We invested US$0.6 million during 1Q14, bringing total investment to US$221.9 million.

2x30MW Mine-mouth Power Plant
We completed the commissioning of PT Makmur Sejahtera Wisesa (MSW) first 30MW unit in 2013.

Expansion of Kelanis Dedicated Coal Terminal
During the quarter, we continued with the detailed planning for the second stage of the Kelanis upgrade that will bring total capacity to 70Mt per year. (end of edited excerpt)