Adaro Energy update: PT Saptaindra Sejati (SIS) ? Mining Contracting

Saturday, January 30 2016 - 02:19 AM WIB

The following is an edited excerpt from IDX-listed energy firm PT. Adaro Energy's quarterly report released on Friday. (ed)

PT Saptaindra Sejati (SIS)
In 4Q15, AI remained SIS?s largest customer, accounting for 54% of SIS?s total overburden removal and 63% of coal production, down from 64% and 67% in the same period last year, respectively, as SIS continues to develop its third party business.

SIS?s third party OB removal in 4Q15 increased 3% year over year to 13.18 Mbcm and its third party coal production at 2.24 Mt was relatively flat compared to the same period in 2014.

  UNITS 4Q15 3Q15 4Q15 vs. 3Q15 4Q14 4Q15 vs. 4Q14 FY15 FY14 FY15 vs. FY14
Overburden Removal Mbcm 29.02 44.02 -34% 40.68 -29% 151.07 173.91 -13%
AI Mbcm 15.58 25.93 -40% 26.14 -40% 85.67 112.14 -24%
SCM Mbcm 0.26 1.08 -76% 1.73 -85% 5.50 4.17 32%
Others Mbcm 13.18 17.01 -22% 12.81 3% 59.90 57.60 4%
Coal Production Mt 6.68 8.12 -18% 8.11 -18% 29.47 30.28 -3%
AI Mt 4.19 5.57 -25% 5.42 -23% 19.60 21.18 -7%
SCM Mt 0.25 0.33 -24% 0.44 -43% 1.11 0.89 25%
Others Mt 2.24 2.22 1% 2.25 -0.3% 8.76 8.21 7%