Adaro Energy update: PT Saptaindra Sejati (SIS) – Mining Contracting
Tuesday, February 12 2019 - 12:49 AM WIB

The following is an edited excerpt from IDX-listed energy firm PT. Adaro Energy's quarterly report released on Monday. (ed)
PT Saptaindra Sejati (SIS)
In 4Q18, SIS recorded a 39% and 37% increase y-o-y in overburden removal and coal production volume to 60.32 Mbcm and 12.49 Mt as volume from Adaro Group and third party customers increased. Overburden removal and coal production volume from Adaro Group were 56% and 82% of SIS?s total volume in 4Q18, respectively.
In 2018, SIS recorded 23% increase in overburden removal volume to 220.52 Mbcm and 27% increase in coal production volume to 44.93 Mt compared to the same period last year. (end of edited excerpt)
| Units | 4Q18 | 3Q18 | 4Q18 vs. 3Q18 | 4Q17 | 4Q18 vs. 4Q17 | FY18 | FY17 | FY18 vs. FY17 | |
| Overburden Removal | Mbcm | 60.32 | 66.46 | -9% | 43.49 | 39% | 220.52 | 179.17 | 23% |
| Coal Production | Mt | 12.49 | 12.37 | 1% | 9.09 | 37% | 44.93 | 35.43 | 27% |