Adaro Energy update: PT Saptaindra Sejati (SIS) ? Mining Contracting

Wednesday, April 30 2014 - 12:27 AM WIB

The following is an edited excerpt from IDX-listed energy firm PT. Adaro Energy's quarterly report released on Tuesday. (ed)

PT Saptaindra Sejati (SIS)
Our mining and contracting subsidiary, SIS, is one of AI?s four mining contractors. In 1Q14, AI remained SIS?s largest customer, accounting for 64% of SIS?s total overburden removal and 74% of its coal getting volume. SIS continued to prioritize AI over servicing new third party business. SIS also continued with mine construction works and pre-stripping activities at our recently acquired Balangan coal project in South Kalimantan. (end of edited excerpt).

MBP Operating Highlights

  Actual Quarter on Quarter Year on Year
  Units 1Q14 4Q13 % Change 1Q13 % Change
Overburden Removal Mbcm 38.59 39.86  (3) 36.17 7
Adaro Mbcm 24.68 25.87 (5) 21.98 12
Others Mbcm 13.91 13.99 (1) 14.19 (2)
Coal Getting Mt  7.23 7.32 (1) 6.00 21
Adaro Mt  5.37 5.25 2 4.04 33
Others Mt 1.86 2.07 (10) 1.96 (5)