Adaro Energy update: PT Saptaindra Sejati (SIS) ? Mining Contracting

Saturday, August 8 2015 - 01:27 AM WIB

The following is an edited excerpt from IDX-listed energy firm PT. Adaro Energy's quarterly report released on Friday. (ed)

PT Saptaindra Sejati (SIS)
In 2Q15, AI remained SIS?s largest customer, accounting for 57% of SIS?s total overburden removal and 68% of coal production, down from 65% and 72% in the same period last year, respectively, as SIS continues to develop its third party business. (end of edited excerpt)

? UNITS 2Q15 1Q15 2Q15 vs. 1Q15 2Q14 2Q15 vs. 2Q14 1H15 1H14 1H15 vs. 1H14
Overburden Removal Mbcm 42.41 35.63 19% 43.96 -4% 78.03 82.55 -5%
AI Mbcm 24.21 19.95 21% 28.52 -15% 44.16 53.2 -17%
SCM Mbcm 2.58 1.57 64% 0.89 190% 4.16 0.89 367%
Others Mbcm 15.61 14.10 11% 14.55 7% 29.71 28.46 4%
Coal Production Mt 7.42 7.24 3% 7.18 3% 14.66 14.46 1%
AI Mt 5.08 4.76 7% 5.20 -2% 9.84 10.58 -7%
SCM Mt 0.15 0.38 -60% 0.08 88% 0.53 0.12 342%
Others Mt 2.19 2.10 4% 1.90 15% 4.29 3.76 14%