Bayan produced 3.7 million tonnes during the second quarter 2011, up compared to the corresponding period last year of 2.9 million tonnes.
The company did not provide coal sales figure during the period. Bayan is targeting to produce 14.5-15.5 million tonnes of coal in this year.
Last year the company produced 12 million tonnes of coal from its eight coal mine subsidiaries, including PT Gunungbayan Pratama Coal, PT Perkasa Inakakerta, PT Wahana Baratama Mining, PT Teguh Sinar Abadi and PT Firman Ketaun Perkasa.
During the first semester, the company?s majority customers, include Malaysian power utility Tenaga Berhad, Taiwan utility firm Taipower, trading firms Noble, Adani, J. Aron Co, Coal & Oil and East India Energy Company. (denny)
| Location name | Concession owner | Date of exploitation or development permit | Expiry date of permit | Percentage of ownership | Total proven and probable reserves (in million metric tonnes)* | Total production (in million metric tonnes) | Remaining reserves as at 30 June 2011 (in million metric tonnes)* | |
| Current period 2011 | Cumulative total production | |||||||
| Block-II | PT Gunungbayan Pratamacoal (GBP) |
August 2, 1999 | July 11, 2029 | 100% | 15.0 | 1.4 | 3.0 | 12 |
| Block-I | PT Gunungbayan Pratamacoal (GBP) |
August 28, 2007 | July 11, 2029 | 100% | 5.0 | 0.2 | 0.3 | 4.7 |
| Block Sepaso | PT Perkasa Inakakerta (PIK) |
August 13, 2007 | March 29, 2037 | 100% | 24.0 | 1.7 | 3.4 | 20.6 |
| Block Satui | PT Wahana Baratama Mining (WBM) |
October 26, 2007 | October 25, 2037 | 100% | 67.0 | 2.1 | 3.4 | 63.6 |
| KW KTN 2005018 | PT Fajar Sakti Prima (FSP) |
July 21, 2005 | July 21, 2025 | 100% | 333.0 | 0.8 | 1.5 | 331.5 |
| KW KTN 2004046 | PT Bara Tabang (BT) |
April 7, 2008 | April 7, 2028 | 100% | ||||
| KW.03PB 0059 | PT Teguh Sinarabadi (TSA) |
April 29, 2008 | April 23, 2038 | 100% | 210 | 0.9 | 1.7 | 19.3 |
| KW.03PB 0058 | PT Firman Ketaun Perkasa (FKP) |
April 29, 2008 | April 23, 2038
|
100% | ||||
| KW.051PB0108 | PT Firman Ketaun Perkasa (FKP) |
October 27, 2009 | October 26, 2011 | 100% | ||||
| Note: *The remaining proven and probable reserves as at 30 June 2011 are based on the survey performed by Minarco Mineconsult, independent geologist, date 30 June 2010 after being reduced by the production since the survey dates. | ||||||||
| **The Group is in the process of obtaining an extension of this permit | ||||||||