CNOOC to cut gas supply to PLN on maintenance
Sunday, November 16 2008 - 10:27 PM WIB
CNOOC Ltd will conduct maintenance on its production platform and gas plant in Pabelokan Island, Java Sea, and South East Sumatra PSC in Mid-December 2008.
During the maintenance period, gas supply to PLN?s Cilegon Power plant would be cut by 25 percemt, CNOOC Indonesia VP Relations & GA Soegiarto Moechammad told Petromindo.Com.
Normally, gas supply to Cilegon was around 60MMCFD.
He, however, said that the maintenance would be completed in less than a week. (godang)