COAL TENDER: EWP-COAL-2012-SP05 & LT03

Thursday, July 19 2012 - 06:29 AM WIB

Summary of Invitation to Bid
For (Sub)-bituminous Coal for EWP Thermal Power Plant

1. Bid No. : EWP-COAL-2012-SP05 & LT03

2. Materials and Quantity to be Procured
○ Materials: (Sub)-bituminous Coal
○ Quantity and shipping schedule

SPEC. Quantity Shipment Schedule

(Loading basis)

EWP-COAL-2012-SP05

SPEC 2

(NCV min 4,600kcal/kg)

130,000MT September to October, 2012

(For Dangjin Power Plant)

EWP-COAL-2012-SP05

SPEC 3

(NCV min 5,100kcal/kg)

65,000MT September to October, 2012

(For Dangjin Power Plant)

EWP-COAL-2012-LT 03

SPEC 2

(NCV min 4,600kcal/kg)

Min 210,000~240,000MT

(70,000~80,000MT?3)

or

Min 260,000MT

(130,000MT?2)

per annum

For five years

October 2012 to March,

2013

(For Dangjin Power Plant)

Evenly spread

1st year

※ The details are as per the ITBs of each tender

3. Procurement Method: International Open Bidding

4. Deadline for Bidding: 11:00 a.m. on July 25, 2012 (Korean Standard Time).

5. Qualification of Bidder: Coal producers, marketing companies or traders those who shall meet the whole requirement of ITB including but not limited to coal quality specification, shipping schedule, quality, etc.

6. Any applicant who wants to receive the relevant documents should inform us of the company's name and e-mail address via e-mail to ?hyeonmikim@ewp.co.kr? or call Hyeonmi, Kim(+82-2-3456-8473) for more information. Please refer to EWP?s homepage www.ewp.co.kr/eng

7. Bid forms should be forwarded to Kyung-Ro, Lee / Managing Director / Procurement Management Division Korea East West Power Co., Ltd. 16th Floor, Dukmyung Bldg., 170-9, Samsung-dong, Gangnam-gu, Seoul, 135-791, Korea.

July 18, 2012.
Korea East-West Power Co., Ltd
Share this story

Tags:

Related News & Products