Consortium ready to supply HSD for PLN unit

Tuesday, September 4 2012 - 01:48 AM WIB

By Godang Sitompul

State-owned electricity company PLN is satisfied with the result of due diligence process on a Singapore fuel depot owned by BP Plc which will be used to supply high speed diesel (HSD) for the Belawan power plant in North Sumatra.

Head of Fuel and Gas Division at PLN, Suryadi Mardjoeki said that the consortium of BP Plc and PT Kutilang Mas is ready to begin the supply of the HSD in October of November of this year for the Belawan power plant.

?We declared that the depot in Singapore owned by BP Plc is ready to supply (HSD),? Suryadi told Petromindo.com Tuesday.

He said that the consortium has won the tender to supply 250,00 kl of HSD per year under a three-year contract.

Editing by Reiner Simanjuntak