Cooper updates Indonesian ops
Thursday, January 28 2010 - 03:00 AM WIB
The following is an excerpt from Cooper Energy's Quarterly Activity Report released on Thursday. (ed)
South Madura PSC (East Java, COE 30% and Operator)
Preparations for spudding the Gigir East-I well in April 2010 are progressing satisfactorily.
The civil works has been awarded and it is expected that work will commence around mid-February. The drilling services have also been awarded.
In addition to the award of the civil works and drilling services, three available rigs have been short listed and the final phase of the tender process is underway. It is expected that the drilling rig tender process will be completed in mid February 2010 and a drilling rig contract awarded at that time.(end of excerpt)