Dart Energy plans re-commissioning at Sangatta in Q3
Friday, June 29 2012 - 08:54 AM WIB
By Romel S. Gurky
Australian-listed energy firm Dart Energy announced that it would carry out re-commissioning of production wells at its Sangatta West coal bed methane (CBM) project in the third quarter of the year.
Dart said in a presentation that the re-commissioning would be followed by the installation of power generator in the following quarter.
Full field development application and approvals are expected next year, it added.
Dart Energy holds 24 percent interest in Sangatta West PSC. The company partners with PT Energy Pasir Hitam Indonesia (Ephindo) with 24 percent and PHE Metana Kalimantan A with 52 percent in developing the Sangatta West PSC.
Editing by Dadan Wijaksana