Donggi Senoro LNG project on track for completion as scheduled.

Thursday, December 6 2012 - 04:16 AM WIB

By Godang Sitompul

Engineering, Procurement and Construction (EPC) works at the Donggi Senoro LNG facility project in Central Sulawesi has reached 70 percent to completion as of November, with a key equipment, a heat exchanger weighting 245 tons with 75 meter in length, scheduled for installation on December 7.

Andi Karamoy, Corporate Secretary of PT Donggi Senoro LNG (DSLNG), the developer of the project, told petromindo.com that the development of the facilities was progressing on schedule.

?The EPC progress as of the end of November has reached 70 percent. On December 7, one key equipment, the Main Cryogenic Heat Exchanger, will start to be installed. This is the heart of the facility,? Andi said.

DSLNG has previously said that the project to construct an LNG refinery facility with a capacity of 2 million tons per year is on track to be completed in the fourth quarter of 2014 as targeted.

Editing by Dadan Wijaksana