Currently, the Company holds 100% shareholding in EBE. Through farm in agreement, EBE currently holds 50.01% working interest (WI) in this block.
Exploration Activities
- Drilling Activities ? Land clearance for Sungai Lahei-1 well road and location, building a jetty, helipad and logistic field office in Luwe Hulu in relation with drilling preparation for Sungai Lahei-1 exploratory well.
- Result- None
- Next Plan:
- Continue to clear the location completing the jetty and logistic field office in Luwe Hulu, followed by building the road and location of Sungai Lehei-1 exploratory well. (US$348,174)
- Preparation to do seismic acuisation and processing, completed to build an explosive bunker for seismic activity while waiting for tender process of seismic acquisition contract. (US$ 44,512.24)
Cost: US$ 392,686.24 (end of release)