EMP's weekly drilling & exploration activities
Wednesday, May 17 2006 - 11:41 AM WIB
WEEKLY DRILLING & EXPLORATION ACTIVITIES
Week ending May 12, 2006
|
|
EXPLORATION / APPRAISAL WELLS | |
PUO-2A, Kangean, East Java, Indonesia | |
Interest |
100% EMP Kangean Ltd (60%), EMP Exploration (Kangean) Ltd (40%) |
Operator |
EMP Kangean Ltd |
Type |
Gas Appraisal |
Status at 05:00hrs |
Setting 9-5/8? casing and temporary abandoning the well |
Next Plan |
Release the rig and await a new one designed for horizontal drilling |
PGRS-2, Kangean, East Java, Indonesia | |
Interest |
100% EMP Kangean Ltd (60%), EMP Exploration (Kangean) Ltd (40%) |
Operator |
EMP Kangean Ltd |
Type |
Gas Appraisal |
Status at 05:00hrs |
Setting casing and resume drilling to TD. Now at the depth of 750 ft |
Next Plan |
Test and complete the well. Target depth 1,000 ft |
|
|
Banjar Panji-1, Brantas, East Java, Indonesia | |
Interest |
50% Lapindo Brantas Inc (50%) |
Operator |
Lapindo Brantas Inc |
Type |
Gas Exploration |
Status at 05:00hrs |
Drilling 12-1/4? hole. Now at the depth of 6,675 ft |
Next Plan |
Drill to casing point and set 9-5/8? casing. Target depth 10,300 ft |
MSBY-02, Malacca, Riau Province Sumatra, Indonesia | |
Interest |
60.49% Kondur Petroleum S.A. (34.46%), PT Imbang Tata Alam (26.03%) |
Operator |
Kondur Petroleum S.A. |
Type |
Gas Exploration |
Status at 05:00hrs |
Drilling with 14? Near Bit Reamer (NBR) to casing point and running casing. Now at the depth of 5,000 ft |
Next Plan |
Set 11-3/4? casing and resume drilling to TD. Target depth 9,638 ft |
DEVELOPMENT WELLS | |
| Wunut-19, Brantas, East Java, Indonesia | |
| Interest | 50% Lapindo Brantas Inc (50%) |
| Operator | Lapindo Brantas Inc |
| Type | Gas Development |
| Status at 05:00hrs | Perforate and flow testing the well. Now at depth 2,960 ft |
Next Plan |
Complete the test and release the rig |
SBR-8, Sambutan, East Kalimantan, Indonesia | |
Interest |
100% PT Sembrani Persada Oil (100%) |
Operator |
PT Semberani Persada Oil |
Type |
Oil/Gas Development |
Status at 05:00hrs |
Setting casing and drilling to TD. Now at the depth of 965 ft |
Next Plan |
Cement 9-5/8? casing, complete the well and release the rig |