EMP's weekly drilling & exploration activities

Wednesday, April 26 2006 - 02:18 AM WIB

PT ENERGI MEGA PERSADA TBK & SUBSIDIARIES
WEEKLY DRILLING & EXPLORATION ACTIVITIES
Week ending April 21, 2006

 

 

EXPLORATION / APPRAISAL WELLS

PUO-2A, Kangean, East Java, Indonesia

Interest

100% EMP Kangean Ltd (60%), EMP Exploration (Kangean) Ltd (40%)

Operator

EMP Kangean Ltd

Type

Gas Appraisal

Status at 05:00hrs

Setting 20? casing and drilling intermediate hole

Next Plan

Run and cement 13-3/8? casing. Resume drilling

  

PGRS-2, Kangean, East Java, Indonesia

Interest

100% EMP Kangean Ltd (60%), EMP Exploration (Kangean) Ltd (40%)

Operator

EMP Kangean Ltd

Type

Gas Appraisal

Status at 05:00hrs

Rigging up is almost complete. Still waiting for the equipment

Next Plan

Complete rigging up and spud the well

 

 

Banjar Panji-1, Brantas, East Java, Indonesia

Interest

50% Lapindo Brantas Inc (50%)

Operator

Lapindo Brantas Inc

Type

Gas Exploration

Status at 05:00hrs

Shutting down and waiting for the mud pump

Next Plan

Repair mud pump and continue drilling

 

MSBY-02, Malacca, Riau Province Sumatra, Indonesia

Interest

60.49% Kondur Petroleum S.A. (34.46%), PT Imbang Tata Alam (26.03%)

Operator

Kondur Petroleum S.A.

Type

Gas Exploration

Status at 05:00hrs

Bottom Hole Assembly (BHA) lost

Next Plan

Plug back and sidetrack the well

 

MSAC-28, Malacca, Riau Province Sumatra, Indonesia

Interest

60.49% Kondur Petroleum S.A. (34.46%), PT Imbang Tata Alam (26.03%)

Operator

Kondur Petroleum S.A.

Type

Oil Exploration

Status at 05:00hrs

Cementing 9-5/8? casing. Drilling final hole section

Next Plan

Log well. Run and set 7? casing

 

DEVELOPMENT WELLS

Wunut-19, Brantas, East Java, Indonesia
Interest50% Lapindo Brantas Inc (50%)
OperatorLapindo Brantas Inc
TypeGas Development
Status at 05:00hrsDrilling final hole section

Next Plan

Finalize and release the rig

 
Wunut 20, Brantas, East Java, Indonesia
Interest50% Lapindo Brantas Inc (50%)
OperatorLapindo Brantas Inc
TypeGas Development
Status at 05:00hrsRunning completion string

Next Plan

Drill intermediate hole to casing point

 

SBR-8, Sambutan, East Kalimantan, Indonesia

Interest

100% PT Sembrani Persada Oil (100%)

Operator

PT Semberani Persada Oil

Type

Oil/Gas Development

Status at 05:00hrs

Rigging down from SBT-3 and move it to SBR-8

Next Plan

Rig up and spud the well