EMP's weekly drilling & exploration activities
Wednesday, January 18 2006 - 06:06 AM WIB
WEEKLY DRILLING & EXPLORATION ACTIVITIES
Week ending January 13, 2006
|
|
EXPLORATION / APPRAISAL WELLS | |
PUO-3, Kangean, East Java, Indonesia | |
Interest |
100% EMP Kangean Ltd (60%), EMP Exploration (Kangean) Ltd (40%) |
Operator |
EMP Kangean Ltd |
Type |
Oil Appraisal (JS53a Field) |
Status at 05:00hrs |
Rig moved from PTO-2 well |
Next Plan |
Drill conductor and construct platform bracings |
|
|
Banjar Panji-1, Brantas, East Java, Indonesia | |
Interest |
50% Lapindo Brantas Inc (50%) |
Operator |
Lapindo Brantas Inc |
Type |
Gas Exploration |
Status at 05:00hrs |
Continue preparation to drill |
Next Plan |
Spud well |
MSED-01, Malacca, Riau Province Sumatra, Indonesia | |
Interest |
60.49% Kondur Petroleum S.A. (34.46%), PT Imbang Tata Alam (26.03%) |
Operator |
Kondur Petroleum S.A. |
Type |
Oil Exploration |
Status at 05:00hrs |
Rig on location |
Next Plan |
Spud and drill well |
MSCN-01, Malacca, Riau Province Sumatra, Indonesia | |
Interest |
60.49% Kondur Petroleum S.A. (34.46%), PT Imbang Tata Alam (26.03%) |
Operator |
Kondur Petroleum S.A. |
Type |
Oil Exploration |
Status at 05:00hrs |
Drilled well to intermediate section |
Next Plan |
Continue drilling the well |
MSDR-01, Malacca, Riau Province Sumatra, Indonesia | |
Interest |
60.49% Kondur Petroleum S.A. (34.46%), PT Imbang Tata Alam (26.03%) |
Operator |
Kondur Petroleum S.A. |
Type |
Oil/Gas Exploration |
Status at 05:00hrs |
Rigging up |
Next Plan |
Spud and drill well |
DEVELOPMENT WELLS | |
PGA-5, Kangean, East Java, Indonesia | |
Interest |
100% EMP Kangean Ltd (60%), EMP Exploration (Kangean) Ltd (40%) |
Operator |
EMP Kangean Ltd |
Type |
Gas Development |
Status at 05:00hrs |
Completion work not done yet. Fish 5? packer out |
Next Plan |
Once well is clean, rerun completion |
|
|
PGC-7, Kangean, East Java, Indonesia | |
Interest |
100% EMP Kangean Ltd (60%), EMP Exploration (Kangean) Ltd (40%) |
Operator |
EMP Kangean Ltd |
Type |
Gas Development |
Status at 05:00hrs |
Temporary suspended, awaiting completion equipment |
Next Plan |
Awaiting for the completion of PGB-4 to complete the well. Run tests and bring gas into pipeline. |
PGB-4, Kangean, East Java, Indonesia | |
Interest |
100% EMP Kangean Ltd (60%), EMP Exploration (Kangean) Ltd (40%) |
Operator |
EMP Kangean Ltd |
Type |
Gas Development |
Status at 05:00hrs |
Drilled production zone to TD and log well |
Next Plan |
Cement casing and run completion |
| LB-11, Malacca, Riau Province Sumatra, Indonesia | |
| Interest | 60.49% Kondur Petroleum S.A. (34.46%), PT Imbang Tata Alam (26.03%) |
| Operator | Kondur Petroleum S.A. |
| Type | Oil Development |
| Status at 05:00hrs | Drilled surface hole and set wellhead |
| Next Plan | Continue drilling well |
| LB-10, Malacca, Riau Province Sumatra, Indonesia | |
| Interest | 60.49% Kondur Petroleum S.A. (34.46%), PT Imbang Tata Alam (26.03%) |
| Operator | Kondur Petroleum S.A. |
| Type | Oil Development |
| Status at 05:00hrs | Rig moved to LB-11 |
| Next Plan | Final report of this well |
| Wunut 14, Brantas, East Java, Indonesia | |
| Interest | 50% Lapindo Brantas Inc (50%) |
| Operator | Lapindo Brantas Inc |
| Type | Gas Development |
| Status at 05:00hrs | Run liner and cement in place |
Next Plan |
Complete well |
A rig is currently being mobilized into Tanggulangin 3 location to workover the well. The rigging | |