The following is excerpt from Ensco International Incorporated’s Contract Status of Offshore Rig Fleet report as of July 15, 2007:

 

Rig Name Design Water Depth Customer/ Status Day Rate Location Est. Avail/Contract Change Comments
ENSCO 67 MLT 84-CE 400 ConocoPhillips High 140's Indonesia Nov. 07 Unpriced options
ENSCO 104 KFELS MOD V-B 400 CHOC
Low 230's
 
Malaysia Oct. 07 Plus cost adjustments. Next to shipyard approximately 40 days. Then to BP Indonesia for 6-months at mid 220's, 6-months at mid 230's, and priced 290-day option, mid 250's plus cost adjustments
ENSCO 108 KFELS MOD V-B 400 BP Mid 170's Indonesia May 08 Rate increases mid Nov. 07 to low 180's, and options May 08 to Nov. 08, mid 190's, then to
Jun. 09, low 200's, and 1-year unpriced option
ENSCO I Barge Rig - Pearl High 60's Indonesia July 07  Next expect to work to Aug. 07, low 70's. Then expect to work to Feb. 08, high 60's