EPC of Mini LPG plant in Banyuasin 73% completed
Friday, February 13 2015 - 02:08 AM WIB
By Febry Silaban
The construction of mini-LPG plant in Musi Banyuasin, South Sumatra has been 73 percent completed, according to a senior official at Ministry Energy and Mineral Resources.
?Under plans, the mini LPG plant will produce 17 ton per day,? Acting Director General of Oil and Gas at the ministry I Gusti Nyoman Wiratmadja said at a hearing with House of Representatives in Jakarta on Wednesday.
The gas will be supplied by PT Medco E & P Indonesia as much as 2.2 mmscfd, he said.
The engineering, procurement, and construction (EPC) works for the project is carried out by PT Hokasa.
Editing by Johannes Simbolon