Monday, October 21 2013 - 09:36 AM WIB
(October 21, 2013) -- Energy World Corporation (EWC) announced that the drilling program for WASAMBO (Walanga - Sampi Sampi - Bonge) gas fields within the Sengkang PSC is progressing on schedule and on 18 October 2013 the 300 feet gas column in Walanga #2 Well was reached at a depth of 2,322 feet.
The gas layer content and pressures are in line with expectations. Interpretations of these results are currently ongoing and the Company will make further announcements when the appropriate competent persons have provided their report and advice to the Company.
In the meantime, Tubing and Well Head Equipment is being installed on the Walanga #2 well in preparation for commercial production.
The rig will then be removed to the Walanga #3 well for the next well drilling operation.
EWC holds a 100 percent interest in Sengkang PSC. (ends)