Finders says FS ontrack on Maluku copper-gold project
Monday, December 4 2006 - 03:07 PM WIB
The company said positive results in all key areas of the project, including copper grades increase by 10% in updated Kali Kuning Resource model, making combined resources now stood at 9.8Mt @ 2.5% Cu (0.5% Cu cut-off)
Increased copper recovery and better concentrate grades are indicated by flotation test work. Indicative results range from 85% to 92% copper recovery with corresponding concentrate grades of 21% and 16%, it said.
The company also said that revised capital cost estimates of US$ 40-45 million for 25,000 tpa off-site Albion plant are in line with its scoping study estimate with mixed-bag of precious metal recoveries as by-product from hydrometallurgical test work.
?We are currently reviewing all aspects of this work, and expect to make a final process decision in early 2007,? the company said.
Finders has around 70 percent stake in the project. (alex)