First shipment of equipments for Sengkang LNG project arrives

Tuesday, August 14 2012 - 02:31 PM WIB

By Ruli Setiawan

ASX-Listed firm White Energy said the first shipment of major equipments together with two cold boxes for its Sengkang LNG project have arrived in Keera and have been successfully offloaded onto site.

The equipments are part of major equipments of 5,000 tons and with an ex-work value in excess of US$200 million (including four cold boxes each with a capacity of 0.5Mtpa) that are on their way to the site.

The Australia-based company also announced that contracts for foundation works have been placed, and these foundation works to enable the equipment to be erected and installed will commence shortly.

Further major equipment together with two additional cold boxes are currently being transported on the MV Fairload to the site and are expected to arrive within the next two weeks.

Shipping of other major equipment such as Siemens Compressors, Electric Drive Motors and Loading Arms will continue during the coming months.

Editing by Dadan Wijaksana