G-Resources initial production on schedule
Tuesday, June 19 2012 - 08:26 AM WIB
Hong Kong-listed gold miner G-Resources Group Limited stated that with some recent commissioning milestone achievements at G-Resources Martabe gold and silver project in Batang Toru North Sumatra currently, the project is on schedule for first gold pour in July 2012.
The company said that significant milestones have recently been achieved at Martabe project, such as the completed construction of the crusher and conveyors.
"First ores were fed through the crusher and delivered to stockpile on 18 Juni 2012," said the company on its press statement today.
The company added that SAG and Ball Grinding Mills water commissioning is completed and ready for ore feed while CIL gold leach tanks water commissioning are still in progress.
"The construction gold room is nearing completion,"said the company.
For piping installation currently is more than 95 percent complete followed by electrical and instrumentation installation which is more than 85 percent complete.