Golar short-listed for Jakarta floating LNG terminal project
Friday, August 27 2010 - 04:14 PM WIB
?The final evaluation of commercial bids is underway with an expectation of a final award decision in the near future,? the company said in Interim Result report released Friday.
The company did not disclose its two competitors.
The company reported in February 2010 that it received a PQ from the consortium for a ~3 MTPA offshore LNG receiving terminal.
The Company also said that another floating LNG receiving terminal by PGN to be build in Belawan, North Sumatra reached a positive project milestone with the appointment of Foster Wheeler as the Project Manager. ?The project appears on track for a Q4 2010 tender,? it said.
PGN is planning to build floating terminal with capacity of 1-2 MTPA. (alex)