Government renegotiates IPP contracts

Wednesday, June 18 2003 - 01:27 AM WIB

The government has completed renegotiations with 26 independent power producers (IPP), raising optimism that there will be no power crisis in the future.

"With the completion of the renegotiations with the IPP, we are ready to move forward. There will be no more power crises next year as some of the IPP projects will enter the stream," Coordinating Minister for the Economy Dorodjatun Kuntjoro-jakti said in a hearing with House of Representatives Commission VIII for energy, environment and science and technology.

Dorodjatun said the dispute with Karaha Bodas Company is the only case left to settle.

"The case is still under litigation by the legal representative of the Indonesian government and Pertamina. An out of court settlement is being pursued by a facilitation team," Dorodjatun added, referring to the state oil and gas company Pertamina.

Known as Tim Keppres 133, after the Presidential Decree No. 133/2001 issued to establish the team, the team was tasked to renegotiate power purchase agreements (PPA) signed by state electricity company PLN and 27 IPPs prior to the economic crisis.

The government put on hold many of the projects in late 1997 as part of the retrenchment program to cope with the economic crisis. PLN, which was financially troubled by the crisis, asked to renegotiate the PPAs, especially with regards the price.

Following the postponement of the project, some of the IPPs decided to file arbitration proceedings against PLN, Pertamina and the government, while others were willing to renegotiate the contracts.

PLN's president Eddie Widiono said PLN would save more than US$5.5 billion in costs thanks to the contractual renegotiations.

Of the 26 IPPs, 14 IPPs agreed to continue their projects under a new pricing scheme, while seven agreed to terminate the PPAs. The government and PLN each agreed to take over two projects, while Pertamina took over one project. The 26 IPPs have a combined power generation capacity of 10,615 megawatt.

As for the seven terminated PPAs, Eddie said, the government is likely to offer them to new investors.

Of the 14 IPPs, who agreed to resume their projects, seven projects are still in process and are scheduled to be finished by 2006/2007. The seven are Amurang power plant, Sibolga, Sibayak, Asahan, Paiton I, Paiton II and Sengkang.

According to Eddie, most of the 14 IPPs have agreed to sell their power at an average of 4.6 U.S. cents per kilowatt per hour (KwH) except for the diesel fired Pare-pare power plant in Makassar at 5.7 U.S. cents and Paiton at 4.9 U.S. cents.

Eddie did not disclose why Paiton would sell at a higher price for its power supply but in the case of the Pare-pare power plant, Eddie said the price was higher because it used diesel fuel.

"Diesel is more expensive than other types of fuel," he said.

Legislator Priyo Budisantoso of the Golkar party praised the completion of the renegotiation, while voicing concern that the new power price agreed upon with the IPPs were still higher than that of other Southeast Asian countries.

"It (the new price) is still not competitive. But it is better than the initial 8 U.S. cents per KwH. Thus, we appreciate the effort," he said. (*)

TABLE: Status of 27 IPPs

No.

Project Name

Fuel Location Capacity (MW)

IPP Company

Status


1. Amurang Coal N. Sulawesi 2 x 55 PT Tenaga Listrik Amurang

Continued

2. Asahan I Hydro N. Sumatra 2 x 90 PT Bajradaya SentranusaContinued
3.Bedugul (unit 1,2) Geothermal Bali 2 x 110 Bali Energy LtdContinued
4. Cikarang Gas W. Java 72 PT Cikarang ListrindoContinued
5. Drajat Geothermal W. Java 1 x 70Amoseas IndonesiaContinued
6. Gunung Salak Geothermal W. Java 3 x 55 Unocal Geothermal Indonesia Ltd.Continued
7.Paiton I Coal E. Java 2 x 615 PT Paiton Energy CompanyContinued
8. Paiton II Coal E. Java 2 x 610 PT Java PowerContinued
9. Palembang Timur Gas S. Sumatra 135 PT Astrigita PrasaranaContinued
10. Pare-Pare Diesel SE Sulawesi 6 x 10 PT Makasar Power CorporationContinued
11. Sengkang Gas S. Sulawesi 80 PT Energi SengkangContinued
12. Sibayak Geothermal N. Sumatra120 PT Dizawarta PowerindoContinued
13. Sibolga A Coal N. Sumatra1 x 100 PT Tenaga Listrik SibolgaContinued
14. Tanjung Jati B Coal C. Java 2 x 660 PT CEPA IndonesiaContinued


1. Cibuni Geothermal W. Java 10 PT Yala Teknosa Geothermal Acquired by PLN
2. Sarulla Geothermal N. Sumatra 3 x 110 Unocal Geothermal Indonesia Ltd. Acquired by PLN


1. Wayang Windu Geothermal W. Java 1x110 PT Mandala Nusantara Power Acquired by Pertamina


1. Dieng (unit 1,2,3) Geothermal C. Java 60 Himpurna California Energy Ltd. Acquired by Government
2. Patuha (unit 1) Geothermal W. Java 2 x 110 Patuha Power Ltd Acquired by Government


1. Cilacap Coal C. Java 400 PT Citra Kartika Daya Terminated
2. Cilegon Coal W. Java 1 x 400 PT Daya Listrik Pratama Terminated
3. Kamojang Geothermal W. Java 60 PT Latoka Trimas Bina Energy Terminated
4. Pasuruan Gas E. Java 500 PT East Java Power Corporation Terminated
5. Serang Coal W. Java 450 PT Power Jawa Barat Terminated
6. Tanjung Jati A Coal C. Java 2 x 660 PT Tanjung Jati Power Company Terminated
7. Tanjung Jati C Coal C. Java 2 x 660 PT CEPA Indonesia Terminated


1. Karaha Geothermal W. Java 2 x 110 Karaha Bodas Co. LLC Arbitration


Share this story

Tags:

Related News & Products