Govt plans to build 4 new LPG depots this year

Monday, February 1 2016 - 05:13 AM WIB

By Febry Silaban

The Ministry of Energy and Mineral Resources is planning to build four LPG storage tanks in eastern Indonesia including in West Nusa Tenggara (NTB), East Nusa Tenggara (NTT), Maluku, and West Papua provinces this year.

?This year we?ll start to build four new LPG depots in Bima (NTB), Kupang (NTT), Wayame (Maluku), and Jayapura (West Papua),? Director General of Oil and Gas at the Ministry of Energy and Mineral Resources IGN Wiratmaja said, hoping that the LPG cylinders can be deployed in 2017.

Planned LPG tanks in eastern Indonesia, 2016-2018

No Location Capacity (MT) 2016 2017 - 2018 Total Investment (Rp billion) Information
Budget (Rp billion) Activities 2017 (Rp billion) 2018 (Rp billion) Activities
1 Jayapura 2 x 1000+Jetty 43.92 Tender & Construction 131.76 43.92 Construction 219.60 FEED completed by Pertamina Dec 2015
2 Wayame 2 x 1000+Jetty 43.92 Tender & Construction 131.76 43.92 Construction 219.60 FEED prepared by Pertamina, to be completed Feb 2016
3 Tenau 2x500 42.90 Tender & Construction 128.70 42.90 Construction 214.50 FEED prepared by Pertamina, to be completed Feb 2016
4 Bima 2x500 43.55 Tender & Construction 130.65 43.55 Construction 217.75 FEED prepared by Pertamina, to be completed Feb 2016
5 Maluku Utara 2x500 - Land acquisition - - Construction -  
  TOTAL 6000 174.29   522.87 174.29   871.45  

Editing by Reiner Simanjuntak