Haddington updates S. Kalimantan coal project
Saturday, August 1 2009 - 02:57 AM WIB
Tabalong Coal Project
Haddington continues to evaluate its coal leases at Muara Uya, Tabalong in South Kalimantan. Further works progressed in order to convert the Tabalong Coal Project from exploration to exploitation status. Government Feasibility and AMDAL (Environmental Approval) documentation was prepared to satisfy government and other stakeholders.
The socialisation process has commenced including public consultation and formulation of directive frame book (terms of reference). Presentation of the AMDAL is scheduled for mid August with feedback and recommendations expected in late September. Final sign-off is expected in November 2009.(end of excerpt)
Editor?s note:
The project is covered by two KP's (Mining Permits) which are held by PT Suryaraya Permata Khatulistiwa (SPK) and PT Suryaraya Cahaya Cemerlang (SCC) and cover 1,993 and 4,315 hectares respectively.
Haddington, through its wholly owned subsidiary PT Minvest Mitra Pembangunan (MMP) has an option to purchase both PT SCC and PT SPK in their entirely.
Haddington has carried out conceptual project feasibility in order to ascertain the annual production limits, infrastructure requirements, transport options and product marketing. Present plans are for annual production and sales of coal at 500,000 tonnes to 750,000 tonnes. Present indications are that the Tabalong project could be in production in early 2010.
The Company has calculated a maiden Coal Resource for the Tabalong coal project. A total estimation of Coal Resource is about 11.3 million tonnes.