IP: PQ invitation for Grati Add On block 2 project

Friday, August 19 2016 - 01:22 AM WIB

GRATI ADD ON BLOCK 2 PROJECT
WITH MINIMUM NET DEPENDABLE CAPACITY OF 150 MW,
PASURUAN - EAST JAVA
No: 002.PENG/DEPPEU/EPC-ADD-ON/IP/2016
INVITATION OF INTERNATIONAL COMPETITIVE BIDDING

As part of the 35,000 MW acceleration program and in order to increase electric power supply to industry, business and household in Jawa-Bali grid, PT Indonesia Power (PT IP), a power generation company which is a subsidiary of PT PLN (Persero), intends to build Grati Add On Block 2 Project with minimum Net Dependable Capacity of 150 MW, Pasuruan ? East Java (?Project?). The Project will add the existing Block 2 with HRSG(s) and Steam Turbine Generator. The Project will be financed by PT Indonesia Power?s own fund.

PT IP invite Bidders, either in the form of Joint Operation or Consortium, to participate in the International Competitive Bidding with post-qualification for the engineering, procurement, construction and commissioning of the Project. The bid will be conducted in 1 (one) Stage with 2 (two) Envelopes.

The general qualification criteria of a Bidder shall be as follows:
1. Bidder shall be a Joint Operation/Consortium between foreign company from OECD country which has diplomatic relation with Indonesia and local company,
2. The maximum number of members in a Joint Operation/Consortium shall be 3 (three) companies,
3. The Bidder shall have experience in last 10 years at least I (one) Combined Cycle Power Plant EPC project with minimum capacity of 300 MW or 2 (two) Combined Cycle Add On EPC project with minimum capacity of 150 MW, which is already successfully in operation,
4. The local company shall be state-owned contractor that have experience in the last 10 years in constructing at least civil work of power plant project, or private local contractor that have experience in the last 10 years in EPC power plant project with minimum capacity of 100 MW which is already successfully in operation,
5. Any member company of the Bidder at the time of bidding process shall not under a suspension or blacklisted by PLN group or any Government Instrumentality for any reason whatsoever, and:
i. in the last 10 (ten) years does not have record of unsatisfactory performance, including poor claims history and defective workmanship, such as 1 (one) power plant project or any other related works which is experiencing delays for more than 1 (one) year, or
ii. has more than 2 (two) ongoing power plant projects or any other related works that have been delayed for more than 6 (six) months.

Applicants may register and collect the Bid Document upon non-refundable payment of DR 15,000,000.- ( shall be transfer to PT Indonesia Power account no 0004464628 at BNI Bank) from August 19th, until August 23rd 2016 from 09.00 am until 03.00 pm at the following address:

PT Indonesia Power
Attn: Procurement Officer
Grati Add On Block 2 Project
with Minimum Net Dependable Capacity of 150 MW
PT Indonesia Power Building 6th Floor
Jalan Gatot Subroto Kav 18 Jakarta
TeIp: +6221-526 7666
Fax: +6221-525 3467
Share this story