KOMIPO opens tender for one million tons per annum of bituminous coal

Tuesday, January 16 2007 - 02:04 AM WIB

Summary of Invitation To Bid
For Bituminous Coal for Boryeong Thermal Power Plant

1. Bid No. : KOMIPO-Coal-2007-LT01

2. Material and Quantity to be Procured
- Material : Bituminous Coal
- Quantity : 1,000,000MT per annum

[Spec 1] NAR min. 5,600kcal/kg (VM 22% ~ 36%)
[Spec 2] NAR min. 5,350kcal/kg (VM max 45%)

- Bidders shall offer at least 250,000MT up to a total of 1,000,000MT.
- Total awarded quantity for Spec1 and Spec2 will be varied upon the bidder's proposal.

3. Term of the Contract : April 1, 2007 ~ March 31, 2010

4. Procurement Method: International Open Bidding

5. Deadline for Bidding : 3:00 p.m. on January 22, 2007 (Korean Standard Time).

6. Qualification of Bidder : Coal producers, marketing companies or traders those who shall meet the whole requirement of ITB including but not limited to coal quality specification, shipping schedule, quality, etc.

7. Any applicant who wants to receive the relevant documents should inform us of the company's name and e-mail address via e-mail to khn99@komipo.co.kr. or,
Please refer to KOMIPO homepage www.komipo.co.kr.

8. Bid forms should be forwarded to
Jeong-Hwan Yun / Senior Manager / Fuel Team, Business Dept.
Korea Midland Power Co., Ltd.
167, Samsung-dong, Gangnam-Gu, Seoul 135-791, Korea.

January 12, 2007
Korea Midland Power Co., Ltd.