Medco?s weekly drilling & exploration activities
Tuesday, October 11 2005 - 02:23 AM WIB
WEEKLY DRILLING & EXPLORATION ACTIVITIES
Week ending October 7, 2005
? |
? |
EXPLORATION / APPRAISAL WELLS | |
Carat-1, Brantas PSC, East Java, Indonesia | |
Interest |
32% through Novus Indonesia Brantas Company |
Operator |
Lapindo Brantas |
Type |
Oil and Gas Development |
Status at 0600hrs |
Killed F- 10 zone, retrieved completion string, prepare to set cement plug. |
Next Plan |
Set cement plug. |
? |
? |
Sukowati -4, Tuban PSC JOB, East Java, Indonesia | |
Interest |
25% through PT Medco E&P Tuban |
Operator |
PetroChina International |
Type |
Oil and Gas Development |
Status at O600hrs |
Prepare to acidized. Found tubing or packer leak |
Next Plan |
Acidizing and production testing |
? |
? |
Jata-4, South Sumatra Extension PSC, South Sumatra, Indonesia | |
Interest |
100% through PT Medco E&P Indonesia |
Operator |
PT Medco E&P Indonesia |
Type |
Delineation |
Status at 0600hrs |
Waiting for Service Rig |
Next Plan |
Completion job with service rig |
| ? | ? |
? |
? |
DEVELOPMENT WELLS | |
Tiaka-7, Senoro Toili PSC JOB, Central Sulawesi, Indonesia | |
Interest |
50% through PT Medco E&P Tomori Sulawesi |
Operator |
JOB PERTAMINA - Medco E&P Tomori Sulawesi |
Type |
Oil Development |
Status at 0600hrs |
Preparing to run DST |
Next Plan |
Run DST |
? |
? |
Mamburungan - 2005-2, Tarakan PSC, East Kalimantan, Indonesia | |
Interest |
100% through PT Medco E&P Kalimantan |
Operator |
PT Medco E&P Kalimantan |
Type |
Oil Development |
Status at 0600hrs |
Setting Top Drive Tool |
Next Plan |
Drilling 6?" hole. Planned TD 9088? |
? |
? |
Kaji Semoga 2005-31, Rimau Block PSC, South Sumatra, Indonesia | |
Interest |
95% through PT Medco E&P Indonesia |
Operator |
PT Medco E&P Indonesia |
Type |
Oil Development |
Status at 0600hrs |
Set 7? casing at 3141?. Completed cementing |
Next Plan |
N/U X-mast tree |
? |
? |
Kaji Semoga 2005-35, Rlmau Block PSC, South Sumatra, Indonesia | |
Interest |
95% through PT Medco E&P Indonesia |
Operator |
PT Medco E&P Indonesia |
Type |
Oil Development |
Status at 0600hrs |
Continued wiper trip, logging job FMT tools, RIH RB 8 ?? to cleaned hole |
Next Plan |
Run casing and testing |
? |
? |
Matra C-6, Rimau Block PSC, South Sumatra, Indonesia | |
Interest |
95% through PT Medco E&P Indonesia |
Operator |
PT Medco E&P Indonesia |
Type |
Oil Development |
Status at 0600hrs |
Completed drilling 12 ?? hole to 3260? |
Next Plan |
Run 9 5/8? casing and continue drilling. Planned TD 5120? |
? |
? |
? |
? |
SEISMIC SURVEY | |
Tarakan 2D/3D, Tarakan TAC, East Kalimantan, Indonesia | |
Interest |
100% through PT Medco E&P Tarakan |
Operator |
PT Medco E&P Tarakan |
Type |
2D/3D Seismic Survey |
Activities |
3D Survey: Line preparation activities (i.e. line clearance, topographic measurement, shothole drilling and recording) have been conducted; The progress of the survey is as follow: |
? |
2D Survey: Line preparation activities (i.e. line clearance, topographic measurement) have been conducted; The progress of the survey is as follow: |
? |
Note: In last week report, 3D and 2D progress is united. |
Next Plan |
Continue with line preparation (2D survey area); drilling shothole and recording data (3D survey). |