Medco?s weekly drilling & exploration activities
Tuesday, October 18 2005 - 08:07 AM WIB
WEEKLY DRILLING & EXPLORATION ACTIVITIES
Week ending October 14, 2005
? |
? |
EXPLORATION / APPRAISAL WELLS | |
Carat-2, Brantas PSC, East Java, Indonesia | |
Interest |
32% through Novus Indonesia Brantas Company |
Operator |
Lapindo Brantas |
Type |
Oil and Gas Development |
Status at 0600hrs |
Tested C-10 zone, swabbed water; C-50 zone swabbed water and gas, TSTM. |
Next Plan |
Free the stuck packer. |
? |
? |
Sukowati -4, Tuban PSC JOB, East Java, Indonesia | |
Interest |
25% through PT Medco E&P Tuban |
Operator |
PetroChina International |
Type |
Oil and Gas Development |
Status at O600hrs |
Prepare to acidized. Found tubing or packer leak |
Next Plan |
Acidizing and production testing |
? |
? |
Jata-4, South Sumatra Extension PSC, South Sumatra, Indonesia | |
Interest |
100% through PT Medco E&P Indonesia |
Operator |
PT Medco E&P Indonesia |
Type |
Delineation |
Status at 0600hrs |
Drilling rig released on September 25, 2005 and moved to Matra 2005-1. |
Next Plan |
Continue completion job with service rig |
| ? | ? |
| Rengas-1, South Sumatra Extension PSC, South Sumatra, Indonesia | |
Interest |
100% through PT Medco E&P Indonesia |
Operator |
PT Medco E&P Indonesia |
Type |
Oil and Gas Exploration |
Status at 0600hrs |
M/U BHA to drill ahead w/ 12 ?" bit |
Next Plan |
Drill ahead with 12 ?" bit to 9 5/8" csg point. |
| ? | ? |
? |
? |
DEVELOPMENT WELLS | |
Tiaka-7, Senoro Toili PSC JOB, Central Sulawesi, Indonesia | |
Interest |
50% through PT Medco E&P Tomori Sulawesi |
Operator |
JOB PERTAMINA - Medco E&P Tomori Sulawesi |
Type |
Oil Development |
Status at 0600hrs |
Completed testing, prepare to move to Tiaka-6 |
Next Plan |
Recompletion at Tiaka-6 well |
? |
? |
Mamburungan - 2005-2, Tarakan PSC, East Kalimantan, Indonesia | |
Interest |
100% through PT Medco E&P Kalimantan |
Operator |
PT Medco E&P Kalimantan |
Type |
Oil Development |
Status at 0600hrs |
Drilling 6" hole at 7809? |
Next Plan |
Continue drilling 6" hole. Planned TD 9088? |
? |
? |
Kaji Semoga 2005-31, Rimau Block PSC, South Sumatra, Indonesia | |
Interest |
95% through PT Medco E&P Indonesia |
Operator |
PT Medco E&P Indonesia |
Type |
Oil Development |
Status at 0600hrs |
Installed X'mast tree, rig relased and move to Kaji Semoga 2005-33 |
Next Plan |
Drilling at Kaji Semoga 2005-33 |
? | ? |
Kaji Semoga 2005-33, Rimau Block PSC, South Sumatra, Indonesia | |
Interest |
95% through PT Medco E&P Indonesia |
Operator |
PT Medco E&P Indonesia |
Type |
Oil Development |
Status at 0600hrs |
Waiting for cuthead line, repaired at Palembang |
Next Plan |
Drill ahead w/ 12 ?" bit to 9 5/8" csg shoe |
? | ? |
Kaji Semoga 2005-35, Rimau Block PSC, South Sumatra, Indonesia | |
Interest |
95% through PT Medco E&P Indonesia |
Operator |
PT Medco E&P Indonesia |
Type |
Oil Development |
Status at 0600hrs |
Completed logging, run 7" casing and move to KS 2005-36 |
Next Plan |
Drilling at Kaji Semoga 2005-36 |
? | ? |
Kaji Semoga 2005-36, Rimau Block PSC, South Sumatra, Indonesia | |
Interest |
95% through PT Medco E&P Indonesia |
Operator |
PT Medco E&P Indonesia |
Type |
Oil Development |
Status at 0600hrs |
N/U BOP stack |
Next Plan |
Drill ahead w/ 8 ?" bit to TD, logging |
? |
? |
Matra C-6, Rimau Block PSC, South Sumatra, Indonesia | |
Interest |
95% through PT Medco E&P Indonesia |
Operator |
PT Medco E&P Indonesia |
Type |
Oil Development |
Status at 0600hrs |
Completed drilling 8 ?" hole to TD (5149?), prepare for logging |
Next Plan |
Logging, run 7" casing and move rig to Matra 2005-2. |
? |
? |
? |
? |
SEISMIC SURVEY | |
Tarakan 2D/3D, Tarakan TAC, East Kalimantan, Indonesia | |
Interest |
100% through PT Medco E&P Tarakan |
Operator |
PT Medco E&P Tarakan |
Type |
2D/3D Seismic Survey |
Activities |
Line preparation activities (i.e. line clearance, topographic measurement, Line Clearance: 334.78 km |
Next Plan |
Continue with drilling shothole and recording data. |