MEO Australia: Seruway PSC operations update
Monday, November 5 2012 - 12:59 AM WIB
Since the last report, 9 5/8? casing has been run and cemented to 2,677mMDRT. After pressure testing of Blow-out Preventers and the 95/8? casing, 8?? hole was drilled to 2,794mMDRT. Mudlog gas shows were observed to increase over the interval from 2,776mMDRT to 2,794mMDRT in the Baong sands.
In response to these gas shows, a 30m full-hole conventional core has been planned from 2,794mMDRT. At 2400 hours (Jakarta time) on 4th November operations were in progress to commence coring.
Progress Summary
Progress since last report:
− Ran and cemented 95/8? casing to 2,677mMDRT
− Drilled 8?? hole to 2,794mMDRT
Present Operation (at 2400hrs Jakarta time, 4th November)
− Preparing to cut 30m core from 2,794mMDRT
Outlook:
− Complete coring and drill 8?? hole to base of Baong sands