Oil, gas projects to start production in 2014
Monday, January 6 2014 - 01:41 AM WIB
The upstream oil and gas authority SKK Migas hopes the projects can begin production on schedule. ?Any delay will affect the national oil and gas lifting this year,? said SKK Migas Public Relations Chief, Elan Biantoro on Sunday.
Some of the projects that are expected to start production this year include the Sisi Nubi 2B in the Mahakam block, with contractor Total E&P Indonesie, which is targeted to produce 350 mmscfd of gas in the first quarter of 2014.
Another is the Senoro gas development project, with JOB Pertamina-Medco Tomoro Sulawesi as the operator, which is planned to begin producing 8 mmscfd of gas and 250 bpd of oil in the third quarter.
There are projects which were supposed to start production in 2014 but were postponed to the first quarter of 2014. They include the Ridho field project, with Odira Energy Karang Agung as the operator, which is expected to produce 1,200 bpd of oil; the Gundih field, which is being developed by Pertamina EP, expected to produce 50 mmscfd of gas and 600 bpd of oil; and the Bayan A project, with Manhattan Kalimantan Investment as the contractor, which is expected to produce 15 mmscfd of gas and 250 bpd of oil.
Elan said that there are three projects which will be closely monitored by SKK Migas with regards to the size of production and the challenges faced. The first is the Bukit Tua field in the Ketapang 2 block, with Petronas Carigali as the operator, which is planned to produce 70 mmscfd of gas, and 20,000 bpd of oil in the first quarter of 2014. The thing that needs to be closely monitored is the process of negotiation of the gas price and the change in the buyer candidate, Elan said. ?Aside from this, the project uses the upstream and downstream scenario, therefore there are strategic policies taken beyond the authority of SKK Migas,? he said.
The same thing happens with the Muriah field in the Kepodan block, which is also operated by Petronas. The project with production of 116 mmscfd of gas relies on the completion of the gas pipeline in the downstream side. ?Construction of the upstream facilities will be completed in October 2014,? Elan said.
The last project is the Banyu Urip field in the Cepu block with Mobil Cepu Ltd (MCL) as the contract. The strategic project is planned to begin production in the fourth quarter of 2014 with targeted peak output of 165,000 bpd of oil. Among of the challenges include social economic issues, and a delay in the EPC process.
?These projects must be closely monitored so that there will no delay,? Elan said, pointing out to a number of measures to make sure the projects would be realized on time including intensive supervision, monthly meeting, and site visit.
| No | Project name | PSCs | Capacity of production facility | Target On-Stream |
||||
| Gas | Liquid | |||||||
| 1 | Peciko 7B - New Platform | Total E&P Indonesie | 170 | MMSCFD | 4000 | BPD | Q1 | 2014 |
| 2 | Sisi Nubi 2B - New Platform | Total E&P Indonesie | 350 | MMSCFD | - | - | Q1 | 2014 |
| 3 | Peluang Development | Santos | 25 | MMSCFD | - | - | Q1 | 2014 |
| 4 | POFD Bekapai Phase 2A | Total E&P Indonesie | - | - | 1021 | BPD | Q1 | 2014 |
| 5 | Muriah Field Development (Kepodang) | Petronas Carigali Muriah Ltd. | 116 | MMSCFD | - | - | Q4 | 2014 |
| 6 | Peciko 7C ? Extension | Total E&P Indonesie | 125 | MMSCFD | 1500 | BPD | Q2 | 2014 |
| 7 | Ridho Field Development | Odira Energy Karang Agung | - | 1200 | BPD | Q2 | 2014 | |
| 8 | Bukit Tua Development | Petronas Carigali Ketapang 2 Ltd. | 70 | MMSCFD | 20000 | BPD | Q4 | 2014 |
| 9 | Java Gas Development Project (PPGJ) ? Gundih | Pertamina EP | 50 | MMSCFD | 600 | BPD | Q1 | 2014 |
| 10 | Bayan A Gas Production Facilities | Manhattan Kalimantan Investment | 15 | MMSCFD | 250 | BPD | Q1 | 2014 |
| 11 | Kerendan Gas Plant | Salamander Energy - Bangkanai | 25 | MMSCFD | 300 | BPD | Q4 | 2014 |
| 12 | Senoro Gas Development - Early Start Up | JOB Pertamina Medco Tomori Sulawesi | 8 | MMSCFD | 250 | BPD | Q3 | 2014 |
| 13 | Banyu Urip Field Development | Mobil Cepu Ltd | - | - | 165000 | BPD | Q4 | 2014 |
Editing by Reiner Simanjuntak