Pertamina, PLN agree on steam price for Kamojang, Lahendong power plants
Saturday, January 9 2016 - 04:37 AM WIB
Confirming an earlier report, Pertamina said that the price of geothermal steam produced by the company for PLN?s Kamojang power plant units 1, 2, and 3 in West Java has been agreed at 6 US cents per kWh, and for unit 4 at 9.4 US cents per kWh.
It added that the price of steam for the Lahendong power plant (units 1, 2, 3 and 4) in North Sulawesi has also been agreed at 6 US cents per kWh.
Pertamina and PLN had earlier engaged in dispute over price disagreement particularly for steam supplied to the Kamojang geothermal power plant.
The statement said that the companies finally reached an agreement following meeting facilitated by State Minister of State Owned Enterprises Rini Soemarno.
Editing by Reiner Simanjuntak