INVITATION FOR REBIDDING
JAWA 2 (PRIOK) COMBINED CYCLE POWER PLANT 800 MW

1. As part of the 35.000 MW Acceleration Program, and in order to increase electric power supply to industry, businesses and households in Jakarta and its surrounding areas, PT PLN (Persero) (hereinafter refer to as PLN) must enhance its generation capacity and strengthen 500 kV transmision loop. To achieve this objective, PLN hereby invites Bidders for the design, execution and completion of the Jawa 2 (Tanjung Priok) Combined Cycle Power Plant 800 MW.

2. PT PLN (Persero) invites sealed bids for an International Competitive Bidding that implementing one stage two envelopes bidding process for a project:
Title: REBIDDING JAWA 2 (PRIOK) COMBINE CYCLE POWER PLANT 800 MW
Net Output (MW): 800 MW ? 10% (site condItion)
Engine: Gas Turbine and Steam Turbine with 2:2:1 configuration

The project is located at the Tanjung Priok Power Plant in North Jakarta. The site is approximately 5,2 hectares as indicated in the plant layout. The bidder shall confirm that the site area is sufficient for this project.

3. The scope of works shall be on a full EPC Fixed Lumpsum basis except for piling works which will be on the unit price basis. The scope comprises design, manufacture, inspection and testing at manufacture?s facility, packing, shipment, insurance, customs clearance, delivery to site, unloading, storing, and handling at site, complete erection, on-site testing and commissioning, performance testing, operation and maintenance during testing and commissioning, warranty and inspection prior to final acceptance of a complete plant. The detail of scope of work is stated on Bid Document.

4. Bidder shall be a company from OECD Country which has diplomatic relation with Indonesia. Where a bidder is an international Joint Venture, Joint Operation, or Consortium, they shall be in affiliation with an Indonesia entity.

5. In order to qualify, Bidders must demonstrate that they have completed at least 1 (one) EPC Contracts which:
- Has been completed within the last 10 (ten) years
- Shall be for a Combined Cycle Power Plant (GT and ST) for 700 MW or higher per Block
- Has achieved a satisfactory record of a minimum 2 (two) years of successful commercial operatiori outside of the Bidder?s country of domicile, and verified with a statement letter of satisfactory operation from the goods/ service user

6. The Proposed of Main Equipments shall fulfill the following requirements:
a. The Gas Turbine Generator (GTG), and the Steam Turbine Generator (STG) shall be originally manufactured in an OECD Country having diplomatic relation with Indonesia.
b. The Heat Recovery Steam Generator (HRSG), Transformer and Other Equipments will be preferred from local manufacturer in Indonesia.
c. Meet all other requirements set forth in the Bid Document.

7. PLN shall finance the project using 30% equity and 70% debt. An export credit agency shall cover at least 50 % of the debt financing. Bidders shall propose the prospective lender who wilt cover the loan without guarantee from the Government of Indonesia and non-collateral.

8. Bidders shall fulfill financial requirement as set forth in the Bid Document. Bidders shall submit with their application a recent valid document.

9. Bidders may register and collect a Bid Document between November 2, 2015 and November 26, 2015 at the address below:
PT PLN (Persero) Head Office
c/o Procurement Officer for REBIDDING JAWA 2 (PRIOK) COMBINE CYCLE POWER PLANT 800 MW
Main Building, 15th Floor, Jalan Trunojoyo Blok M l/135, Kebayoran Baru, Jakarta 12160
Phone +6221- 7261875, 7261122, Fax +6221- 7227060

10. Proposed Bid shall be submitted in 1 (one) original, 1 (one) hard copy and 1 (one) electronic copy by hand no later than 14:00 PM local time on November 27, 2015 to the above address in sealed envelopes clearly marked as mentioned point 2 above.