PLN: PQ invitation for Banten coal-fired IPP project

Tuesday, November 16 2010 - 12:58 AM WIB

PLN (PERSERO)
INVITATION
NOTICE FOR THE PRE-QUALIFICATION OF APPLICANTS FOR THE IMPLEMENTATION OF 1 X 660 MW BANTEN COAL FIRED STEAM POWER PLANT INDEPENDENT POWER PRODUCER PROJECT

PT PLN (Persero) (PLN) intends to select a potential project sponsor (the ?Project Sponsor) to develop Banten Coal Fired Steam Power Plant IPP Project in Banten Province, Republic of Indonesia. The selected Project Sponsor will develop, finance, construct and operate the Project with net capacity of 1 x 660 MW on a Build-Own-Operate-Transfer (BOOT) basis pursuant to a long-term Power Purchase Agreement (PPA) up to 25 (twenty five) years; and finance and construct the associated 500 kV transmission line, which will be transferred to PLN as a special facility.

This Pre-qualification is open to interested party or parties, either domestic or foreign partnership with domestic, who have previous experience in implementing power generation projects and will be selected through a competitive bidding process from a pool of Applicants that meet the qualification criteria set forth in Pre-Qualification Document. The Qualification Criteria will be based on three categories represent the Applicant?s ability to develop IPP projects, Its power generation experience and its financial strength.

PLN invites interested parties to submit PQ?s applications in accordance with the criteria set forth in the Pre-Qualification Document. Only Applicants whose Qualification Statements demonstrate that they meet all of the criteria set forth in the Pre-Qualification Document will be invited to submit bids for the Project.

Pre-qualification Document may be collected from November 18, 2010 to December10, 2010 at the following hours: 09.00 - 15.00 West Indonesia Standard Time after payment of a non refundable fee in the amount of Rp 15.000.000,- (fifteen million rupiahs) at the following address:

PT PLN (Persero)
c/o Chairman of Procurement Committee for IPP Banten CFSPP
Main Building, 13th Floor
Jalan Trunojoyo Blok M 1/135
Kebayoran Baru - Jakarta 12160
Indonesia
Tel : +62-21-722 7049
Fax: +62-21-725 1511

Applicants should submit to PLN, their application for the pre-qualification during normal business hours at or before 14.00 West Indonesia Standard Time on or before December 14, 2010.

Jakarta, 16 November 2010