INVITATION FOR PRE QUALIFICATION
JATIGEDE HYDRO ELECTRIC POWER PLANT PROJECT 2 X 55 MW
PT PLN (Persero) called ?PLN? hereby invites for Pre-Qualification for the design engineering, procurement and construction, including commissioning of Jatigede Hydro Electric Power Project. The project located in Jatigede sub distric, Sumedang Regency, West Java Province is as follow:
| Project Title | Gross Output (MW) | COD unit I (months) | COD unit 2 (months) |
Jatigede Hydro Electric Power Plant Project (HEPP) |
2 x 55 |
46 | 48 |
PLN intends to Pre-Qualify Applicants as EPC Contractors in the form of Single Company, Joint venture/Joint Operation or Consortium to undertake the engineering, procurement, construction, testing and commissioning including qualification of main equipment (i.e turbine and generator). The qualified Applicants will be invited for the International Competitive Bidding process (ICB) of the above project. International Competitive Bidding will be conducted in accordance with PLN?s bidding process. The proposed project will be financed by PLN under Export Credit Agency in the scheme of Buyer?s Credit, without Government Guarantee.
The scope of works shall be on a turnkey basis, include but not limited to site investigation and site development, engineering, procurement of goods, construction, testing and commissioning, including the warranty. Summarise scope of work will be define in Pro-Qualification Document.
Pro-qualification criteria will be based on the Applicant?s satisfactory demonstrated of:
1. Successful as main contractor or as a member of JV/JO/Consortium for engineering, procurement, construction, commissioning and commercial operation of Hydro Electric Power Plant with project size of 30 MW per unit or larger,. located outside of Applicant registered home country or in Indonesia, duly completed and successfully operation minimum 2 (two) years.
2. Successful experience in design and manufacture of main equipment (i.e turbine and generator) shall be proven at least demonstrated by 2 (two) years satisfactory operation by owner with minimum capacity 50 MW
3. Financial capability as evidenced by audited balance sheet and profit/loss statement for the last 5 (live) years. The Applicant?s financial capability should be sound and satisfactory and shall be evaluated in term of net profit and total assets.
4. The Commitment Letter from potential lender to finance the project.
Further detail information are given in Instruction to Applicants within P0 document.
Applicant may register and collect the Pre-qualification document from October 09, 2012 after payment of a non refundable fee in the amount of Rp. 5,000.000,- (Five million Rupiahs) at:
c/o Chief of Procurement Committee for Jatigede Hydro Power Project 2 x 55 MW
Main Building, 15th Floor, Jalan Trunojoyo Blok Ml/135, Kebayoran Baru, Jakarta 12160
Phone +6221- 7261875, 7251234, ext: 1236/1667/1862; Fax +6221- 7227060
Applications in one (1) original, two (2) copies and one (1) electronic copy (PDF file) shall be delivered by hand not later than November 26, 2012, within office hour to the above address in the sealed envelopes with clearly marked as mentioned as invitation for Pre Qualification Jatigede Hydro Electric Power Project 2x55 MW?
Applicants will be advised in due course, of the result of evaluation on their applications. Only pre-qualified Applicants will be invited to bid. It is expected that the Invitation to Bid will be made in December 2012.
Procurement Committee