REVISION OF INVITATION FOR BID
RIAU GAS FIRED POWER PLANT (PEAKER) 200 MW

1. As part of the 35.000 MW Acceleration Program, and in order to increase electric power supply to industry, businesses and households in Sumatera, PT PLN (Persero) (hereinafter refer to as PLN) must enhance its generation capacity. To achieve this objective, PLN hereby invites Bidders for the design, execution and completion of the RIAU Gas Fired Power Plant Peaker 200 MW which consist of EPC and 5 (five) years operation and Maintenance (O&M).

2. PT PLN (Persero) invites sealed bids for an International Competitive Bidding that implementing a two stages bidding process for a project: -
Title: RIAU GAS FIRED POWER PLANT (PEAKER) 200 MW
Net Output (MW): 200 MW + 10%
Engine: Gas Turbine or Gas Engine (Dual Fuel)

The project is located at Balai Pungut, Riau Province. The bidder shall confirm that the site area is sufficient for this project.

3. The scope of works shall be on a full EPC Lumpsum basis except for piling works will be on the unit price basis. The scope comprises design, manufacture, inspection and testing at manufacture?s facility, packing, shipment, insurance, customs clearance, delivery to site, unloading, storing, and handling at site, complete erection, on-site testing and commissioning, performance testing, operation and maintenance during testing and commissioning, warranty, inspection prior to final acceptance of a complete plant and shall provide a five (5) years term of service for operation and maintenance starting from Taking Over Date. The detail of scope of work is stated on Bid Document.

4. The Bidder shall be Local Company and shall form Joint Venture/Joint Operation/Consortium with company from Organization for Economic Co-operation and Development (OECD) Country members which has diplomatic relation with Indonesia, The Leader of Joint Venture/Joint Operation/Consortium shall be Local Company. The Bidders shall include O&M Company as a member of Joint Venture/Joint Operation/Consortium.

5. In order to qualify, Bidders must demonstrate that they have completed at least 1 (one) EPC Contract (with minimum sharing 20%) as follows:
a) Within the last ten (10) years;
b) Two (2) years of successful commercial operation for the project
c) EPC Contract shall be for a power plant;
d) The EPC Contract shall be for Gas Turbine power plant project larger than 25 MW and for Gas Engine power plant project larger than 6 MW.

For Leader of Joint Venture/Joint Operation/Consortium:
- Gas Turbine Power Plant or Gas Engine Power Plant or Combined Cycle Power Plant for 80 MW or larger, or Steam Power Plant for 10 MW or larger per unit having achieved satisfactory records for one (1) year respectively.

For O&M Company member shall be from Local Company or Company from OECD country members and demonstrate their Operation and Maintenance (O&M) management capabilities:
- Power Plant O&M services work within the last fifteen (15) years)
- O&M Contract for Open Cycle or Combine Cycle Power Plant or Coal Fired Steam Power Plant.

6. The Proposed of Main Equipment shall fulfill the following requirements:
a. The Gas Turbine Generator (GTG) or Gas Engine Generator (GEG) shall be manufactured in OECD Country members which in diplomatic relation with Indonesia.
b. Transformer shall be locally manufactured.
c. Meet all other requirements set forth in the Bid Document.

7. PLN shall finance the project using 30% equity and 70% debt. An export credit agency shall cover at least 50 % of the debt financing. Bidders shall propose the prospective lender who will cover the loan without guarantee from the Government of Indonesia and non-collateral.

8. Bidders shall fulfill financial requirement as set forth in the Bid Document. Bidders shall submit with their application a recent valid document.

9. Bidders may register and collect the bid document from June 8th - August 19th 2016, after payment of a non refundable fee in the amount of Rp 15.000.000,- (fifteen million Rupiah) at the address below:
PT PLN (Persero) Head Office
c/o Lahmeyer for RIAU GAS FIRED POWER PLANT (PEAKER) 200 MW
15th Floor, Main Building, Jalan Trunojoyo, Block M I/135, Kebayoran Baru, Jakarta Selatan 12160, Indonesia,
Tel: +62(21)725 1234; Fac: +62(21)722 7060.

10. The Proposal shall be submitted in one (1) original, one (1) copy and one (1) electronic copy by hand not later than 14:00 PM local time on August 22nd, 2016 to the above address in the sealed envelopes with clearly marked as mentioned as Project of point 1 above.

Jakarta, June 8,2016
Procurement Officer for Riau Gas Fired Power Plant (Peaker) 200 MW