PLN?s coal supply tender attract 12 bidders
Thursday, July 1 2010 - 06:56 AM WIB
State electricity firm PT Perusahaan Listrik Negara (PLN) said on Thursday that pre-qualification phase of the tender to supply 5 million tons per annum low-rank CV coal for its 14 power plants attracted 12 bidders.
?Actually there were 40 bidders, who came to pick up the tender document but only 12 bidders returned the document until the submission dateline on June 30,? PLN?s primary energy director Nur Pamudji told Petromindo.com.
He did not give the name of the bidders.
The coal supply contracts have a duration of 5 years. (bernard)
The list of power projects
| No | Coal-fired Power Plant Project | Capacity (MW) | Location |
| 1 | Labuan Angin (Non Accelerate) | 2 x 115 | N. Sumatra |
| 2 | PLTU 2 Banten | 2 x 300 | Labuan, Banten |
| 3 | PLTU 1 Jawa Tengah | 2 x 350 | Rembang, C. Java |
| 4 | PLTU 1 Banten | 1 x 625 | Suralaya, Banten |
| 5 | PLTU 1 NTT | 2 x 8.2 | Ropa, Ende, East Nusa Tenggara |
| 6 | PLTU 1 Jawa Barat | 3 x 330 | Indramayu, W. Java |
| 7 | PLTU 2 Jawa Timur | 1 x 660 | Paiton, E. Java |
| 8 | PLTU NTB | 1 x 25 | Jeranjang, Lombok, West Nusa Tenggara |
| 9 | PLTU Sulawesi Tenggara | 2 x 10.4 | Kendari, S.E Sulawesi |
| 10 | PLTU 2 Sulawesi Utara | 2 x 25 | Amurang, Manado, N. Sulawesi |
| 11 | Atambua (State budget) | 4 x 6 | East Nusa Tenggara |
| 12 | PLTU 3 Banten | 3 x 315 | Teluk Naga, Banten |
| 13 | PLTU 1 Jawa Timur | 2 x 315 | Pacitan, E. Java |
| 14 | PLTU 2 Jawa Barat | 3 x 350 | Pelabuan Ratu, W. Java |