PLN signs deal with CFK
Tuesday, January 31 2012 - 09:02 AM WIB
The Power Purchasing Agreement (PPA) was signed on Tuesday by PLN President Director Nur Pamudji and his CFK counterpart Zainal Muttaqien in Jakarta, setting the price at Rp 759.23/kWh (coal price is assumed at US$66.55/ton).
The plant is currently being developed within the complex of PLTU Embalut Unit 1 and Unit 2 in Kutai Kartanegara, East Kalimantan, with a combine capacity of 2x22.5 MW. The Embalut (expansion) pushes up total power generation to 95 MW.
The Embalut (expansion) is a project with a Built, Own, Operate and Transfer (BOOT) scheme, with PLN taking over the plant from CFK as the developer after the contract expires in 25 years. Estimated to cost about US$85 million, the plant will commercially operate in 2015 and aims to supply the province?s power system.
CFK is also the Independent Power Producer (IPP) for PLTU Embalut Unit 1 and Unit 2.
Editing by Dadan Wijaksana