PLN tenders another spot coal supply for Labuan power plant

Saturday, July 24 2010 - 03:35 AM WIB

State electricity firm PT Perusahaan Listrik Negara (PLN) on Saturday announced a spot tender to supply coal to its 2x300 MW Labuan power plant in Banten.

PLN invited coal contract of work (CCoW) or PKP2B, KP/IUP holders to participate in the spot tender. It requires the coal companies have not current contract with Labuan power plant.

Bidders should also have a track record to supply coal to PLN or PLN?s subsidiaries.

Bidders should offer in cost, insurance and freight (CIF) terms

PLN said that the coal should have a CV of between 4,250 kcal/kg to 4,700 kcal/kg (GAR), a total moisture (TM) of ≤ 35%, Ash ≤ 6% (Ar), sulphuric content of ≤ 0.35 % (Ar)

Bid documents can be obtained at PLN (Persero)'s head office at Jl. Trunojoyo Blok M 1/135, Kebayoran Baru, Jakarta 12160 from July 23 through 26 with bid submission scheduled on July 26, 2010. (kanti)

Quantity Shipment Schedule
50.000 ton (Lot 1) 9 August, 15 August, 21 August, 29 August, 2 September, 7 September 2010
50.000 ton (Lot 2) 12 August, 17 August, 23 August, 29 August, 1 September, 6 September 2010
40.000 ton (Lot 3) 12 August, 16 August, 27 August, 31 August, 3 September 2010
40.000 ton (Lot 4) 13 August, 16 August, 30 August, 4 September, 5 September 2010