PLTU Holtekamp to be on stream this year

Tuesday, August 16 2016 - 03:32 AM WIB

By Cepi Setiadi

State owned electricity firm PT PLN stated that the 2x10 MW PLTU Holtekamp coal-fired power plant, in Jayapura, Papua Province, is expected to be on stream this year.

Haryanto WS, PLN?s Business Director for Maluku and Papua regions told Petromindo.com on Monday that currently the first unit of 1x10 MW of the power plant has entered the commissioning phase.

?For the second unit, or another 1x10 MW, is targeted to be on stream by the end of this year,? he said.

Editing by Reiner Simanjuntak