The paper quoted Poso Energy President Director Ahmad Kalla as saying that total investment requirement for the three power plant projects is estimated at US$1.5 billion.
He said that the company has obtained loan from Bank Rakyat Indonesia to help finance the construction of the Poso 1 hydro power plant project with capacity of 3x30 MW.
Poso Energy Director Alimuddin Sewang said that construction progress of the Poso 1 project has reached 28 percent, and is projected to start commercial production in December of 2017.
The Poso 1 project is located near the 3x65 MW PLTA Poso 2 hdyro power plant, which has been in production, distributing electricity to Central and Sulawesi via transmission lines built by the company and state-owned electricity firm PT PLN.
Alimuddin said that the company plans to start construction of the Poso 3 hydro power plant project in 2018 in the hope that it could start production in 2022. (*)