Press Release: APBI's response to reports on coal supply problem at Suralaya
Thursday, April 22 2004 - 02:24 AM WIB
APBI members that supply coal to Suralaya power plant are PT Adaro Indonesia (1 million tons), PT Berau Coal (1 million ton), PT Kideco Jaya Agung (2 million tons), and PT Tambang Batubara Bukit Asam or PTBA.
In the past, PTBA faced obstacles due to problems in railway transportation.
PT Adaro, PT Berau, and PT Kideco have thus far always fulfilled their contractual obligations of coal delivery. Moreover, during critical situations, the companies have several times took part in helping solve problems.
APBI hopes that all parties professionally fulfill their contractual obligation according to business ethics.
APBI believes contracts clearly stipulates rules regarding of obligations, rights, and penalties. As a consequence, any breach of contract should be professionally resolved.
Contact: Bambang Susanto, Executive Director of APBI, Address: Gedung Gajah Unit A,B,C 5th Fl. No A2, Jl. Saharjo No 111, Jakarta Selatan, Tel: 021-8303632. (*)
